One year of heat from Reichenhall for Bad Reichenhall
23.01.2023
One year of heat from Reichenhall for Bad Reichenhall
This concept was awarded the first tender for iKWK systems by the Federal Network Agency in Berchtesgadener Land in 2018 - as one of only five projects.
As a result, Stadtwerke Bad Reichenhall awarded the contract for the general technical planning to Gammel Engineering to build the new energy center and the district heating network.
During the concrete planning phase, a power plant was created consisting of
two natural gas CHP units, each with 3.4 megawatts of electrical (MWel) and 3.2 MW of thermal (MWth) output,
two ammonia groundwater heat pumps with 1.5 MWth and
two power-to-heat plants of 1.2 MWth each. This also includes
three heat storage units of 250 m³ each and one
peak load boiler with a heat output of 5 MW.
The heating network was developed in the first expansion stage with a route length of around 6 km, slightly less than expected in the feasibility study
The entire power plant was integrated into the existing Stadtwerke underground bus garage - which of course requires meticulous as-built surveys and 3D planning.
20 years at Gammel Engineering - congratulations Tom!
We were able to celebrate a special anniversary today: February 15 marked the 20th anniversary of Anita Ebenslander joining Gammel Engineering. Two decades that stand for commitment, precision and exceptional reliability.
Handover of donations from our Christmas fundraising campaign
Having already reported on the results of our Christmas donation campaign, we are now delighted that all three donations have now been handed over in person.
It was particularly important to us not only to hand over the donations symbolically, but also to visit the facilities on site and gain an insight into their valuable work.
The Friends of Cabrini House was founded over 10 years ago and sees itself as a community of people who want to support the children, young people and adult residents of Cabrini House.