One year of heat from Reichenhall for Bad Reichenhall
23.01.2023
One year of heat from Reichenhall for Bad Reichenhall
This concept was awarded the first tender for iKWK systems by the Federal Network Agency in Berchtesgadener Land in 2018 - as one of only five projects.
As a result, Stadtwerke Bad Reichenhall awarded the contract for the general technical planning to Gammel Engineering to build the new energy center and the district heating network.
During the concrete planning phase, a power plant was created consisting of
two natural gas CHP units, each with 3.4 megawatts of electrical (MWel) and 3.2 MW of thermal (MWth) output,
two ammonia groundwater heat pumps with 1.5 MWth and
two power-to-heat plants of 1.2 MWth each. This also includes
three heat storage units of 250 m³ each and one
peak load boiler with a heat output of 5 MW.
The heating network was developed in the first expansion stage with a route length of around 6 km, slightly less than expected in the feasibility study
The entire power plant was integrated into the existing Stadtwerke underground bus garage - which of course requires meticulous as-built surveys and 3D planning.
On October 13, 2026, we were pleased to welcome Ms. Annette Bauer, coordinator, and Ms. Anna Portner, president of the hospice association, to our facility. As part of our Gammel Family Social Fund, we presented them with a donation of 850 euros.
Groundbreaking Ceremony for the New Cabrini School Building
A forward-looking construction project will begin in Offenstetten with a ceremonial groundbreaking on October 2, 2026. A modern building complex for approximately 220 children and adolescents will be built in two phases.
Groundbreaking for 226 apartments—and a strong signal for the heating transition!
New housing is being built on the site of the former Prinz-Leopold Barracks in Regensburg.
On Friday, October 1, the groundbreaking ceremony was held for 226 subsidized apartments—adding another important component to the Innovation Quarter.